You can mark a cadence step as High priority and give it a deadline. Klenty then tracks whether each of those activities was done in time. Priority status shows the live state of each activity, and Priority Reports summarises the results.
Where to find it
Setting a priority: open the cadence step's settings and choose Priority.
Priority status: add the Priority status column on the Calls and Tasks pages.
Priority Reports: Reports → Priority Reports.
All three appear only if your plan includes priority tracking.
How to set it up
Make sure each rep has set Working hours (Settings → User settings → Working hours). Deadlines are counted in working time only.
Open a cadence, open a step's settings and select Priority. The panel reads Mark this activity as High Priority.
Switch Priority from Normal to High.
Under Deadline, enter days, hours and minutes. The default is 15 minutes.
Save the step. Klenty tags each activity from that step as high priority and tracks whether it's completed within the deadline.
Priority status values
Status | Meaning |
Within | Still inside the deadline, or completed before it |
Nearing | Less than 15 minutes of the deadline left |
Exceeded | The deadline passed before the activity was completed |
Priority Reports
For each user, the table shows Manual Email, Calls and Tasks, each split into Priority Activities, Within Deadline and Exceeded Deadline. Use User to pick team members. A custom date range can cover up to 90 days.
Good to know
You can set priority on call steps, task steps and manual email steps. It isn't available on automatic email steps, or on call and task steps that are set to be skipped.
If a rep has no working hours set, no deadline is calculated for their activities.
Regular users can change a step's deadline only if their admin has given them that permission.
Priority Reports has no export.